Transport Minister inspects Alexandria metro, tram, high-speed rail projects

Minister of Transport Kamel El-Wazir inspected on Sunday, November 8, 2026, construction works on Alexandria’s metro project, the rehabilitation and development of the Raml Tram and Alexandria and Borg El-Arab Stadium stations on the first line of the high-speed electric train network.

The tour was part of efforts to implement President Abdel Fattah El Sisi’s directives to accelerate the completion of mass transit projects in line with their schedules.

Alexandria Governor Ayman Attia, members of the House of Representatives and Senate representing the governorate, along with officials from the National Authority for Tunnels, the General Authority for Roads and Bridges and companies implementing the projects accompanied the minister.

El-Wazir began his tour by inspecting the first phase of the Alexandria Metro, which stretches 21.7 km from Abu Qir to Misr Station and comprises 20 stations.

He reviewed construction works at the stations and maintenance workshops in Abu Qir and Kafr Abdo and also travelled in a track inspection vehicle from Montaza to Ghabrial to assess preparedness of completed sections.

The minister also followed up on construction of Tahiya Misr traffic corridor beneath the metro line, extending from Abu Qir to Kafr Abdo, which is designed to facilitate traffic and ease congestion.

El-Wazir said the project represents a major step forward in sustainable green public transport. It aims to increase the line’s maximum capacity from 2,850 to 60,000 passengers per hour per direction, reduce journey times from 50 to 25 minutes, and shorten train intervals from 10 minutes to two and a half minutes. These improvements are expected to ease traffic congestion and reduce emissions, he added.

The minister said the metro would provide interchange services with the Cairo-Alexandria railway at Misr and Sidi Gaber stations, and with the Raml Tram at Sidi Gaber and Victoria stations. It will also connect with the Rashid railway line at Maamoura station.

The metro is also planned to integrate with the first high-speed electric train line at Alexandria and Borg El-Arab stations and the fourth high-speed train line at New Abu Qir station.

El-Wazir also inspected the Tahiya Misr traffic corridor beneath the Alexandria Metro between Abu Qir and Kafr Abdo stations, which is expected to improve traffic flow, reduce congestion, strengthen connectivity between different areas and enhance road safety and efficiency.

The minister then inspected the rehabilitation and development project of the Raml Tram, extending 13.2 km and comprises 24 stations.

He reviewed ongoing works at workshops and stations, as well as progress in supplying 30 modern tram units.

The project will preserve the tram’s historic identity while increasing its capacity from 4,700 to 13,800 passengers per hour per direction, reducing journey times from 60 to 31 minutes and shortening intervals between services from nine to three minutes, Wazir said.

Upgrade works are expected to improve service regularity and ease congestion. He noted that the Raml Tram would connect with the Cairo-Alexandria railway at Sidi Gaber station and with the Alexandria Metro at Sidi Gaber and Victoria stations, facilitating transfers between different modes of transport and integrating the governorate’s urban transit network.

At the end of the tour, El-Wazir inspected Alexandria and Borg El-Arab Stadium stations on the first line of the high-speed electric train network, which runs from Ain Sokhna to El Alamein and Matrouh.

The minister reviewed progress in construction and finishing works, stressing the project’s importance in connecting Alexandria with new cities, industrial zones and tourist destinations, as well as integrating it with the Alexandria Metro, the national railway network and other transport systems.

The project will support both passenger and freight transport and contribute to comprehensive development, he said.

The minister directed officials to intensify work across all projects, adhere to established implementation schedules and ensure the highest standards of quality and safety.

He stressed that integrating the projects was essential to modernizing Alexandria’s transport system and providing safe, modern services for residents.

Source: MENA

, ,